on 11-20-2018 2:01 AM
Hi guys,
Is there a way if we can configure to create only one inspection lot for the material and batch for a HU managed material at the time of GR?
Currently I have setup material to create inspection lot with Origin 01, but system is creating inspection lot for each HU in the delivery, however in our scenario we want to create only one inspection lot per material and batch.
Thanks
Dear Navaid Kamran,
thank you for the details provided.
There is a very good documentation on SAP Help, how system works when QM and HU is involved:
'Quality Inspection for Handling Units'
Please read the documentation for the details.
Have a nice day,
Albert
***
Read and follow the 'SAP Community Rules of Engagement' at
https://www.sap.com/community/about/rules-of-engagement.html
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Albert,
Thanks for sharing, I have gone through it before its a very good document for inspecting HU managed materials but my problem is not to perform inspection on HUs even though material is HU managed.
During GR we receive multiple HUs but inspection is done on the pool sample from each HUs if its pass the whole Batch with all the HUs will be moved to Unrest..
I was thinking to use physical sampling drawing procedure but still system is generating pool sample for each HU in the delivery. Do you think any other way we
Best Regards
Navaid
User | Count |
---|---|
99 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.