SCOPE OF CHECK IN STO DELIVERY (CH WITH B)

HELLO EXPERTS,

I have got situation where we create 100's of deliveries everyday through STO and SAME Batch being assigned (where as we have many other batches available in system) in all the deliveries...even though there is not enough stcok.

here the condition is we donot complete PGI Immediately, we will be doing collective PGI on next day, Problem come here while posting once available stock exhausted then we will get error message no stock exists PGI will be through an error.

*I want system to assign the batch till stock exists then go to other batch.*

I am using Availability check CH with B (Delivery) in Material master, while batch determination in delivery scope of check is as follows:

Stocks - Include safety stock - SELECTED

Replenishmen Lead time - Check without RLT - SELECTED

In/outward movement - All Selected

Incl.depen.reservat. - Do not check

Inc.rel. order reqs - Do not check

incl. planned orders - X All planned orders

Incl. Production orders - X Take all production orders

Where i can configure in system to meet this requiremet, your earliest help will well appreciated...

Thanks in advance..

With best regards,

SAP USER

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    Jan 19, 2010 at 08:35 AM

    Hi

    Kindly go to the t - code OVZ9 and for the combination below

    Availability check CH

    Checking rule B

    Tick the include deliveries in inward/outward movements

    REgards

    Damu