Hi All

I defined a new calendar for shipping point called H6 ( 6 working days) . This calendar is assigned to a X shipping point. When i create a sales order i see the system is proposing 7 day also for the below

SO=> Item => Schedule lines=>Click TAB Shipping ...........we can see the dates determined for

1)Goods issue date

2)Loading date

3)Material avail.date

4)Transportation Plan. Date

The issue is H6 Calendar is with 6 working days (7th Day.. Sunday) i,e starting from Monday to Saturday. But system is proposing dates for the above on Sunday also .

Can anyone through light on how the Shipping calendar influence the above 4 Dates. I believe when H6(6 working days)shipping calendar is assigned then system should consider 6 working days in a week .