dear consultants,

kindly i have a confusion about WC time planning,

1. if i define the setup time in WC and when create production orders system calculate setup times for each order.

but in practical production for the first order in the morning we do setup but for next orders suing the same machine and product, we produce using the machine without re-setup. how to fix this problem?

Accepted Solutions (1)

Accepted Solutions (1)

rupesh_brahmankar3
Active Contributor
0 Kudos

This message was moderated.

Former Member
0 Kudos

Dear Mr. R Brahmankar ,

thank you for replaying m to me,

but i using procss industry and setup type and group is not working in PPPI could guide how to solve this problem

regards,

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

For operations and phases, you can now maintain the fields 'Setup group category' and 'Setup group key' on the 'General data' detail screen please check. If you select an entry in OPG6 the 'Resource setup group' transaction and you jump to the setup transition detail screen for the selected setup matrix and reciep group counter.

SPROProduction Planning for Process IndustriesMaster DataResource-Define Transition Matrix (Tcode= OPG6)

Please refer the sap hlep for details,

Regards,

R.Brahmankar

Former Member
0 Kudos

my question is answered

thank you sir,

Former Member
0 Kudos

Hi Essam,

Can you tell how you solved this issued step by step.

Thanks & Regards,

Dev

Answers (0)