Skip to Content
avatar image
Former Member

PS budget report

I use report S_ALR_87013558, in the result , there is a column called "REM ORD PLAN"(next to "commitment" column), for one project, there are 3000 USD, , may i know how this figure is derived, thanks

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

3 Answers

  • Best Answer
    Dec 23, 2009 at 05:16 AM

    search in forum with " rem ord plan" You will get lots of material IS available.

    WIth Regards

    Nitin P.

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Dec 23, 2009 at 05:22 AM

    Hi,

    Rem Ord Plan = Network Planned cost - (Actual + Commitment). Refer SAP note 178837.

    Regards

    Avisek Bhardwaj

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jan 14, 2010 at 03:38 AM

    done

    Add comment
    10|10000 characters needed characters exceeded