Dear COPC Guru,

In PM order, the component tab, there are the material and required quantity , currently default setup is the plan cost = MAP * this quantity. I would like to use other quantity field,could you advice, any proper to do it. where I can define another plan quantity field so that product costing on service order can calculate plan cost based on this customized quantity.

thanks in advance.

Cathy

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi

Why don't you use different order type for services? so that when you do service you can use the same qty field but the purupose will be met.

Regards

Bala

Former Member
0 Kudos

Hi,

I dont think so this is possible in standard way , unless you do the SAP program modification. But could you please tell me why you want to do this , so that there could be better way to do that?

Regards

Ranjan Kumar

Former Member
0 Kudos

Dear two,

Thanks, the reason I need to have this is because the company need to compare targeted ( or planned) quantity versus the actual part consumption. and the targeted/planned is pre-defined every beginnning of the year.

Can I have your opinion, how to achieve this, thanks.