Hi Expert ,

Please help me to find out the Material Cost in Cost Planning , I have attached materials in a Network activities , PR has also rised with respect to that materials . But in Cost Planning CJ40 Materials Cost not appearing in Network/Order Column or Planned value Column .

I have checked my Control Key it is Determine Cost Planned checked . Cost Variant also i have checked it is correct.

Pls suggest how i will get materials cost in Cost Planning Report.

Accepted Solutions (0)

Answers (5)

Answers (5)

sanjita
Explorer
0 Kudos

Thanks Every One

Kehkashan
Participant
0 Kudos

In transaction OPSB ,check the costing variant is maintained for the Planning profile used in Project profile

sunil_yadav2
Active Contributor
0 Kudos

Sanjita,

Please check setting related to Networks.

thanks

Sunil

praveen_vanm
Participant
0 Kudos

Hi Sanjita,

Could you please check the network parameter type settings

If plan cost calculation is 0 it will not calculate

Thanks

Praveen

kenmelching
Active Contributor
0 Kudos

Are you using Valuated or Non-Valuated Project Stock?

Check the Network Profile settings in config on the Activities tab for a Cost Element in the material planning.

Also see SAP Note 2461220. In the case of non-valuated stock see Note 1940612.

sanjita
Explorer
0 Kudos

Hi Sir ,

I have taken Valuated Stock.

In Network Profile Costing Element is also given for activities.

Pls tell me why costs not reflecting?

Thank You,