on 11-09-2018 8:20 AM
Hi Expert ,
Please help me to find out the Material Cost in Cost Planning , I have attached materials in a Network activities , PR has also rised with respect to that materials . But in Cost Planning CJ40 Materials Cost not appearing in Network/Order Column or Planned value Column .
I have checked my Control Key it is Determine Cost Planned checked . Cost Variant also i have checked it is correct.
Pls suggest how i will get materials cost in Cost Planning Report.
Thanks Every One
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
In transaction OPSB ,check the costing variant is maintained for the Planning profile used in Project profile
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Sanjita,
Please check setting related to Networks.
thanks
Sunil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Sanjita,
Could you please check the network parameter type settings
If plan cost calculation is 0 it will not calculate
Thanks
Praveen
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Are you using Valuated or Non-Valuated Project Stock?
Check the Network Profile settings in config on the Activities tab for a Cost Element in the material planning.
Also see SAP Note 2461220. In the case of non-valuated stock see Note 1940612.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
101 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.