REPORT TO CHECK DIFFERENCE G.R DATE AND U.D DATE FOR A INSP LOT

Hi

I want to track how many dates it has been taken to clear a insp lot for a G.R. So I am looking for a report which shows these days or a report which have G.R date and U.D for inspection lot.

Please guide if there are any reports for this.

Thanks

Dhananjay

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Dec 15, 2009 at 11:13 AM

    Dear Dhananjay

    This is available in MCXA, MCXC report as lead time. Lead time is nothing but time taken for clearing the lot after GR

    Regards

    Gajesh