Dear.

I want to make a cost estimation (CK11N,CK40N) with fixed scrap quantity (BOM) : length(not component scrap, operation scrap).

But system ignore the scrap when cost is estimated.

my system using IS-cable solution.

pls. let me know.

Thanks

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

Check whether you maintain cost component structure for those raw material with cost element assignment.

Regards,

Sreekanth