We come across a situation where process orders have past scheduled date and they have released status.

And when we run MD02, these process orders are not getting rescheduled. Users have to reschedule them manually selecting each one separately which is time-consuming.

Is there way to reschedule these process orders in MD02 or MD03 automatically pls ?. Thanks in advance

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • 3 days ago

    Hello ..

    As per Std SAP procedure, only planned orders will get re-scheduled not with Production or process order. If you want to re-schedule for multiple order, you can use std. T-code COHVPI and select Scheduling option.


    Best Regards,

    Kumar Semmalai

    Add comment
    10|10000 characters needed characters exceeded

  • 3 days ago

    Hi Kumar, Thanks you so much for your help and it's a great answer.

    I am going to try it.

    One more short question pls, COHVPI has below programs in it, any idea we can use these program to schedule in the background ?.

    Screen Program: PPIO_ENTRY