12-14-2009 5:25 AM
Hello All,
I am facing an issue when I try to activate the funded program as an account assignment element in BCS. The path is IMG>Public Sector Management>Funds Management Government>Budget Control System (BCS)>Budgeting>Basic SettingsUse of Master Data>Activate Account Assignment Elements in Budget Control System
The error is as below
Funded program not active with FM area 1000
Message no. FMCU034
Diagnosis
In FM area 1000 the status of funded program is set to "mandatory" or "optional" . The funded program is not active in this FM area and should not be used for budgeting.
Procedure
If you want to use the funded program for budgeting in this FM area, you should first activate it for FM posting.
Otherwise, set the status to "Not used" in budgeting.
Please sugges what needs to be configured in order to activate funded program in SAP..
Reponse is high appreciated.
Best Regards
Abishay Solomon
12-14-2009 10:42 AM
Hi Abishay,
Check first, what is the setting in IMG - Public Sector Management - Funds Management Government - Budget Control System (BCS) - BCS Budgeting - Basic Settings - Use of Master Data - Activate Account Assignment Elements in Budget Control System. Set the setting to Not used' and only then try to activate the funded program.
Regards,
Eli
12-14-2009 12:08 PM
Hi Eli,
Thank you for your input.
But the issue is, I want to use Funded program as account assignment element in BCS. when I try to change the status from Not Used to Optional in IMG > Public Sector Management > Funds Management Government > Budget Control System (BCS) > Budgeting > Basic Settings > Use of Master DataUse of Master Data > Activate Account Assignment Elements in Budget Control System the below error is occures.
Funded program not active with FM area 1000
Message no. FMCU034
Diagnosis
In FM area 1000 the status of funded program is set to "mandatory" or "optional" . The funded program is not active in this FM area and should not be used for budgeting.
Procedure
If you want to use the funded program for budgeting in this FM area, you should first activate it for FM posting.
Otherwise, set the status to "Not used" in budgeting.
Thank you.
Abishay Solomon
12-14-2009 2:26 PM
Hi,
But did you set it here? IMG - Public Sector Management - Basic Settings - Activate Account Assignment Elements.
Regards,
Eli
12-14-2009 3:08 PM
Hi Eli,
I have activate the Funded Program in IMG > Public Sector Management > General Settings for Public Sector Management > Basic Settings: Account Assignment Elements > Activate Account Assignment Elements
But still i am not able to activate the Funded program in BCS as Account assignment element.
Please suggest
Best Regards
Abishay Solomon
12-14-2009 3:47 PM
That's very stange: if you say, that in FMISPS table (the IMG path that I mentioned), the funded program is switched on and you still cannot activate it in BCS, open OSS message.
01-22-2010 1:51 PM
Abishay ,
where do you get this error? During customization or during entering data in a tranaction?
Nick
03-30-2010 7:31 PM
Hi Nicholas Zahiri
Sory bit late ..because today only i activate BCS....
I'am also facing same problem "Activation of Funded Program " then after activation as my friend mentioned above .. logout out from the system complete and then log in ... problem will resolve
in my case after activation also getiing a error funded program is not active .. then i logout & login the funded program got activated with any error
Hople it will help you
Regards
Prakash Sharma