Skip to Content

how to exclude project stock requirment during mrp run

Dear Expert,

I am purchasing a material with lot size as HB (Maximum stock level) and mrp type as VB(manual re order point)

The same material is committed in PM order with special stock -2(Project stock) reservation for WBS element

now when I run MRP, system creating two planned order. One as per the VB(manual re order point) and second one from WBS element

now my requirement is system should not consider any requirement from WBS element( project stock) during mrp run

please advice

Faisal

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Nov 23, 2016 at 03:14 PM

    Hello

    You can use BAdI MD_CHANGE_MRP_DATA to do that. See the blog https://blogs.sap.com/2014/10/01/making-an-element-not-relevant-to-mrp-using-badi-mdchangemrpdata/ for details.


    Regards,
    Caetano

    Add comment
    10|10000 characters needed characters exceeded