hi,
please tell me can i avoid users to not to give schedule line qty more than target qty.....
is it possible.....
Hi friend,
yes it can be possible.....
there is a message for it,it may be a warning in your case.... just turn it to error,
Go to spro--->Material management>Purchasing->Environment data--->define message systems...
Go here select your message....it may be some thing like M06xx
select the message and turn it to error......
Now while the user will crete a schedule line in Me38 he will not be able to create schedule line ....
Hope it is usefull.....