on 12-10-2009 5:35 AM
Dear All,
There is a need to do mass change in value for field Confirmation control Key in PO / SA. Some of them have PO history. If we have PO history system wont allow to change conf. ctrl key. Also since it is a production system we can not cancel previous po histories. This is in SAP 4.7 where we dont have mass change tcode for Scheduling agreements.
Can we maintain the values thru table entries. like using se16n maintain entries check box. This option is greyed out. can we activate that & do this requirement.
please suggest.
hi Greetings!
The confirmation control key can not be changed in the scheduling agreement if GR for item had already been posted. If the GRs can be canceled , it is possible to change the confirmation control in the SA item.
Version 4.7 do not support Mass change of scheduling agreements, hence you have to either create a SCAT or BDC to perform the task.
Gobinathan G
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
85 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.