Dear Gurus,

We have impletemented Item level release strategy for PR.

There was old strategy exisitng only one level release, then we have implemented new release strategy which is multiple level release.

Now the question, there are some PR are released completed for old strategy,. if we change the old PR with old strategy - which was release completed, the system triggeres new release strategy, which over writes the old strategy even though it was release completed status.

Please advice

Regards