Skip to Content
0
Dec 09, 2009 at 08:59 AM

Price Change in Scheduling Agreement

3358 Views

Dear All,

I have created a SA for one material. Here we want to procure that material for 10 plants/Company codes. So i have created 10 different line items. After partial GR the price got changed for this material. Now I want to change the price which effects from today onwards for all the plants/CC. Is there anyway so that instead of changing the price in all the line items, i will change once, so that new price will apply to all the line items. Looking for inputs

regds,

CB