PurReq in APO SNP interactive planning cannot be seen in R3 MD04. What could be the reason?

Accepted Solutions (0)

Answers (4)

Answers (4)

Former Member
0 Kudos

Hi

Try the following:

1. Check the SNP transfer to OLTP settings in SPRO. Check whether the SNP orders are allowed for transfer.

2. Check the distribution definition for the specific plant and external procurement if maintained.

3. If all the settings are fine check the CIF queues in CIF manager. (/n/SAPAPO/CQ)

If there are any blocked queues check the error, correct it and then activate the queues again.

4. If no queues exist in queue manager try CIF reconcile program. (Tcode: /n/SAPAPO/CCR)

Check for the differences and push the queues to ECC / R/3

Hope this would be helpful.

Thanks

Swaroop

Edited by: Swaroop Patil on Dec 10, 2009 10:51 AM

Former Member
0 Kudos

Hi,

I am sorry I had mentioned Distributon demand it should be Distribution defination.

Thanks,

Harsh

Former Member
0 Kudos

Hi,

Please check for the Distribution Demand settings in the Config, but please let me know if it happening for all products or for all the products. Also releasing the change pointers has to be done using the tranaction /sapapo/c5.

But before that please check the queue using transaction /sapapo/cq.

Also run the CCR for bringing the two systems APO and ECC in sync. for all the transactional data.

Thanks,

Harsh

Former Member
0 Kudos

Hi

1) Check the queues

2) Check the distribution definition whether through change pointers

then you need to manually transfer using transaction /sapapo/c5

3) Check the transfer to oltp settings in snp customisation

4) Check the distribution definition in customisation

Regards

R. Senthil Mareeswaran.