Dear Gurus,
In a particular work center I have 3 standard activities: setup time, machine time and labor time.
I have defined a capacity for machine, i.e. used capacity category 001. There I have given the formulae to calculate the total capacity for setup and machine time. In the scheduling tab I have given the scheduling formulae for setup and machining time.
The result given by the system is perfect, i.e. it is calculating the capacity and scheduling these two activities properly.
Now I want to generate the capacity of labor time and also want to schedule it, since after machining there is a considerable time spent on the products by labor. To generate the capacity I can create a new capacity category and the result will be reflected in the planned orders (or production orders) in a new line item. But how can I schedule it along with setup and machine time? I have tried this by giving the scheduling formula of labor time as other formula in the scheduling tab of the work center. But it has not worked. I general, to schedule more than two parameters what needs to be done?