Skip to Content
avatar image
Former Member

CIF Delta transfer - PIR

Hi

I have included the fields LIFAB and LIFBI ( available from and available to dates of a Purchase info record) of EINA table in BD52 for delta transfer.

When i update the Purchase info record with the available from and available to dates and do a CFM3, the corresponding T-Lane in APO is not getting updated.

We want this transfer to take place thru delta transfer and not thru a intial transfer which is scheduled on a longer periodic gap.

Any thoughts on this pls..

Regards

Joe

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    Mar 03, 2010 at 11:49 AM

    the combination of Plant, material, P-Org in the Integration model decides the updates

    Add comment
    10|10000 characters needed characters exceeded