Hi Expert,
As we know that confirmation has to be maintaned for each work order confirmation.
Current condition, we also have to maintained confirmation for each work order sub-operation.
Is there any possibility that only operation level of work order that need to be confirmed? instead of sub-operation level? in assumption that work order created with both operation and sub-operation
illiustration:
Operation 0010 Greasing
Sub operation 0010/0011 cleanning
Sub operation 0010/0012 inspection
Confirmation conducted for operation 0010 Greasing only, instead of all operation and sub operations
Thanks
Pls Help
Rgds