Hi
I wanted to make saturday working for a particular date in a work centre
In cr02 , i went to capacities , intrevals and shift
entered 12/12/2009
length of cycle - 7
work days - 1
Deleted lines from monday to friday and kept saturday
still now i create a production order for 12/12/2009 system says saturday not a working day ?
Please suggest how to make saturday for work centre working ?
Also let me know will mrp create planned order if we make it a working day