Skip to Content
0
Dec 09, 2009 at 01:51 AM

saturday working

32 Views

Hi

I wanted to make saturday working for a particular date in a work centre

In cr02 , i went to capacities , intrevals and shift

entered 12/12/2009

length of cycle - 7

work days - 1

Deleted lines from monday to friday and kept saturday

still now i create a production order for 12/12/2009 system says saturday not a working day ?

Please suggest how to make saturday for work centre working ?

Also let me know will mrp create planned order if we make it a working day