Hi friends,
I wish the PPDS to pick alternate modes in DS board or automatic run, using reschedule/SAP0001 function(hope this is the correct one). I made following settings
I have a ppm with alternate resources. Each resource has different capacity consumption(hope this is ok?)
Resources are finite capacity
DS strategy is finite slot/forward, select any mode is active, lowest mode priority is set to O, while modes are A & B. In scheduling sequence no selection is made(don't know what to select)
Created multiple PP orders (infinite strategy/backward scheduling) at the end of planning period. This schedules orders on mode A resource. I wish the system pick the alternate mode when I reschedule/SAP0001 function. This is not happening with the above settings. Welcomes any suggestion.