Hello,

I want to manage in MEQ1 same quota between 2 suppliers A and B with 2 different purchasing schedule agreements so that I have for a dependent requirement of 100 for a component, 50 components buyed from supplier A ( schedule line of 50 items ) and 50 components buyed from supplier B.

This was done using formula :

Quota-allocated quantity + Quota base quantity

-


= Quota rating

Quota

In MEQ1, I have the same quota rating for the two suppliers.

After launching MRP ( MD41 ) , in MD04 it does not work. A supplier always "win".

Could someone help me ? Thanks.

( ERP SAP ECC 6 )