Dear gurus,
I have never worked in PS module before. Now I have the following task:
There is Project, Network and WBS. I inserted material for operation in WBS and exploded the material.
Now the system must create requirement for this material but NOT for components of BOM. How can I configure the system?
P.S. We don't use MRP and we can't change Material Master Data.
Edited by: Azat Fayzullin on Dec 8, 2009 12:44 PM