" NO SUBSEQUENT DOCUMENT FOUND IN ACCOUNTING"

Dear All,

After Creating Purchase order we created the GRN, for this GRN Accounting Document is generated

Then we completed Invoice verification. For this invoice verification Document Number also generated

However when I click on "Follow-On Documents" it gives error message :

No subsequent document found in Accounting

Long text of error message also attached below:

No subsequent document found in Accounting

Message no. RW011

Diagnosis

All documents generated in Financial Accounting for object type 'RMRP',

reference document number '5174048773' and organizational unit '2009' should be displayed.

System Response

No accompanying documents were found in Financial Accounting

The reason what i guess for this error is....

one more user was doing one big invoice verification due to this big invoice verification the Database got locked.

all users got locked error. Because after he stopped this big invoice all documents got posted correctly.

So I try to cancel this invoice Its giving error message:

" Reversal not possible, accounting document for the ref. does not exist"

Please suggest how to resolve this issue.

Regards,

Shivaji

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

2 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Dec 08, 2009 at 08:53 AM

    Hi,

    Check if the material is created as non valuated.

    If material is not created as non valuated, another reason is that the account assignment category using which you created your PO has tick in "GR Non valuated"

    For checking account assignment go to SPRO --> Materials Management --> Purchasing --> Account Assignment --> Maintain Account Assignment Categories

    If GR Non valuated is ticked, remove the tick & save it.

    Thanks,

    Rajesh

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Dec 09, 2009 at 08:15 AM

    This message was moderated.

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.