Dec 08, 2009 at 06:43 AM

COR3

47 Views

Request your expertise in addressing the below issue.

The Planned Cost column in the T.Code COR3 (Process Orders) is appearing as blank in spite of the FG material having the Standard Cost. This is because the Standard Cost is executed once in a month and at client, it is done at the month end (mostly last week of the month). The system shows the planned cost from the date of execution of Standard Cost to the month end date (30th/31st) only. For the balance days ie 1st of next month to the date of standard cost execution of next month, the system doesnu2019t show the planned cost. It means that the system refers to the standard cost run in a month and reflects the planned cost only after the execution of the process. Hence, we are required to capture the planned cost from the standard price as the same remains constant for 1 month period (date of execution to date of execution of standard cost).

Can somebody suggest a reply.

Prasad