Hello,
I hope you can help me, I have a little (big) problem with the content.
We want an index of productivity based on profit centers represent in BI.
First, I want to extract the master data.
In the normal SAP, I have found an extractor, which extract the employee, profit center and the planned working hours. This data is transferred via the ALE interface cProjects.
Here, I don't find a matching extractor / InfoObject. Is there not something like this?
I found the InfoObject CPR_BPARTN, but no extractors think of how they are filled?
Furthermore, I have not found a place where the hours booked improve the transfer appears, exclusively Projects with the planned number of man-days. Did I miss something?
We have the BI_CONT 7.03 Patchlevel 9.
Thanks for the help and best regards
Lars Goldhahn
PS: Hope you understand me 😊