Former Member
Dec 07, 2009 at 12:31 PM

Sub contracting

41 Views

Dear friends,

In our scenario, the header has special producrement for subcontracting. During MRP the purchase requisition is created for subcontracting item, but, the child the the subcontracting items which are to be sent out does not create any planned order or purchase requisition. In MD04 it shows only SUBREQ. But if there is any depreq then it will combine together and give the planned order. so, basically it is expecting a depreq along with subreq for generating Reciept element. But if it has only SUBREQ then there is no reciept at all. This has created lot of problem. Pls guide. this is stopping go live in APO.

Thanks

Vinay