Hi All,

We have a scenario,

There are 3 plants, and one head office, here H.o considered as a plant.

MRP is run at each plant level and head office level and the requirement is to conloidate all the STO PR's from thiese 3 plants to one PR

at H.O, because the H. O is doing the procurement of materials.

Goods are received at HO sloc and from there it is distributed to the other plants using STO process.

what should be done to acheive this process.

Any inputs?