In RFx functionality bet MM-RFx, buyer creates Requisition in MM asks for one product using RFx and supplier will say that he will submit the alternate material using RFx response, then will the PR created by buyer affects in backend system or does he need to create a requisition again and send it to RFx and again RFx response will be given by supplier.

Regards

Micheal

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • avatar image
    Former Member
    Dec 07, 2009 at 06:43 AM

    Hi

    As of SRM 7.0, bidder can submit the bid with alternate materials. Once the alternate items get accepted by the buyer then he can create the follow on document for the same RFx response with new alternate item. No need to create a new RFx. But i am not quite sure about updating the back end PR.

    Rgds/ Kiran

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hi Michael,

      I meant that PR item would be fulfilled and would also have a reference to the right PO item(even though the material in PR is different from that of the PO).

      Hope this explains

      Regards

      Sumat