Dec 04, 2009 at 12:35 PM

How to set CRTD->REL for a project consist of more than 100 WBS elements

578 Views

Dear Experts,

Now our clients is encounting such a problem:

There is a WBS structure consists of ONE Level 1 WBS code, serveral Level 2 WBS code and hundreds of Level 3 WBS code. All the Level 2 WBS are created automatically according to the data transferred from another system via interface. Level 1 and Level 3 WBS can be created mannually in project builder. And all the status of Level 2 WBS are set to CRTD once they are created automatically.

Level 1 WBS(Let's call it A) has already been set to REL. Only one Level 2 WBS (let's call it A-00) was still CRTD because *it was created after level 1 WBS A was set to REL.* And there are as much as 120 Level 3 WBS(let's call it from A-00-01 to A-00-120) was created under Level 2 WBS A-00 mannually. Now how can I set all the level 3 WBS status from "CRTD" to "REL"?

I have tried following two methods but both of them are failed.

A. Directly set Level 2 WBS A-00 or Level 3 WBS A-00-01to REL (in both CJ20n and CJ02) but the system show a Message No. BS013 falut:

Object A has system status REL, According to this status, transaction "Particially release project" is not allowed"

B. Set Level 1 WBS A to REL(in both CJ20n and CJ02) but the system runs extremly slow and finally the feedback comes to a ABAP error of "Run time error" after more than 30 minutes.

Did any of you face similar situation? Any suggestion for this issue are appreciated.

Regards,

Atom