Dec 04, 2009 at 04:57 AM

Budget Check at Root WBS Element

148 Views

Hi Experts

I have created a Project with one root WBSelement (R). Below this I have created two elements (A & B).

I have kept a budget of Rs.1000/- at 'R' and 'A'. No budget is kept at 'B'. In budget tolerance settings the 'error' is kept on PR and PO.

I purchase material worth Rs.1000/- (ME51, acc.ass.'Q') on element 'A'.

When Material is received at 'A' , I consume it on a NWActivity below 'B'.

In reports (e.g. S_ALR_87013558) the budget is exhausted at Project level , that is at element 'R'.

But I am again able to raise PR for Rs.1000/- at element 'A'. The system is not checking the overall budget at root level 'R'.

Is this standard? What should I do If I want to pu a check at overall project level budget?

Johri