Hello gurus,
can anyone please explain to me this behavior:
We have got a material with Base Unit of Measure PC (piece) and another unit of measure PCK (package) = 250 pieces. Order Unit is PCK.
We maintained a Info Record with a price of 50$ per 1.000 pieces (!).
Now, when I create a new PO and try to order 1 PCK, I would expect the system to determine a price of 12,50$, because 1.000 pieces cost 50$ and 1 PCK contains 250 pieces.
But instead, the price is 50$.
Any ideas on this one? I know I could just change the price in the Info Record, but I just do not understand what the system is doing hereu2026
Thanks in advance
Alica