Hi Experts,
In PRD client Service PO with Planned Delivery Cost is created, But after releasing SES that creates MIGO document which doesn't showing any planned del.cost & hence also in MIRO. In PO this condition is entered at header level.
However the cycle is appearing ok in DEV client. So pls. tell any probable solution for this.
Thanks in Advance.
Amit