Hello gurus

I'm using BCS on ECC6 and it is a first project regarding a FM module. I have tested "Return" process on FMBB and found that a current budget was decreased on FMRP_RW_BUDCON. but, a consumable budget was not changed. Is it a right process on BCS ?. I have tested as below :

Before Budget Return : consumable bg : 1000 consumed bg : 0 available bg : 1000 current bg : 1000

run Return process on FMBB : BCS value type (B1:budget) Proces (RETN: return) Document type (0001: Budget)

amount (1000)

After Budget Return : consumable bg : 1000 consumed bg : 0 avaliable bg : 1000 current bg : 0

I don't understand why consumable bg was remained after current bg was 0. anyways i have run "Return" process with BCS type(R1:release) and Document type (0002: Release) once more, and then a cosumable bg was 0.

i need your advice about the "Return" process on BCS.

Regards,

MK