Skip to Content
0
Former Member
Dec 02, 2009 at 04:25 PM

Flex Planning: key figure view

65 Views

Hello, we've implemented Flexible planning (custom info-structure) and when we're running MC94 and want the key figure view, it takes more than 90 second to explode and the "scroll down" function from there takes forever...

Context:

Table S510 is planned and has 150k entries (sales history)

Table S510E has 45k entries (Planning hierarchy)

Chararcteristic are :Material >Sales rep >Customer.

MC7F: parameter were reduced to the minimum

I read and Apply OSS consulting notes 133919 / 560657 based on performance issues....

Created indexes and it had no impact.

The performance seems to be related to the planning hierarchy size (Table S510E).

I had good results with a planning hierarchy (Table S510E) with size +/- 1000 entries.

My question is:

Is there someone using Flexible planning that has same or more data in their info-structure and have good performance?

Is there any workaround known or other solutions?

Thank you!