Hi Friends

1.Buyer asks supplier to send 3 items with 10qtys each, supplier will send 2 items with 8 qty and the remaning he will send it later on, Is this scenario possible in std in MM-SUS.

2. If buyer asks 3 items and if supplier sends 2 items, can the buyer send only the changed line items to SUS

3. Conversion of open POs to SUS pos

Regards

Emil