CTM overplanning

Former Member
0 Kudos

hi

I've maintained Safety Day's Supply as 10 days. When i run CTM, the Days supply planned is way beyond 10 days and goes more than 70 days.

Any idea for such planning.

Thanks & Regards

Joe

Accepted Solutions (0)

Answers (4)

Answers (4)

Former Member
0 Kudos

Hi Joe,

Please confirm whether your issue is resolved

Regards

R. Senthil Mareeswaran.

Former Member
0 Kudos

ok

Former Member
0 Kudos

Hi Joe,

Please check SAP note 855229

Regards

R. Senthil Mareeswaran.

Former Member
0 Kudos

Hi Joe,

Please look into the following aspects.

1) Check whether safety stock method is maintained alongwith

safety stock days of supply

2) Check any target days of supply maintained in material master

3) Check is there any inconsistency of orders, stocks between

APO & R/3

4) Check whether consider safety days supply is checked under

supplies tab of ctm profile

Regards

R. Senthil Mareeswaran.

Former Member
0 Kudos

Hi Senthil

Pls find inline my reply...

1) Check whether safety stock method is maintained alongwith

safety stock days of supply - SS method " SZ" is maintained

2) Check any target days of supply maintained in material master - "Not maintained "

3) Check is there any inconsistency of orders, stocks between

APO & R/3 - " No Inconsistencies "

4) Check whether consider safety days supply is checked under

supplies tab of ctm profile - "Checked in CTM profile "

Can you still look into why it plans excess.

regards

Joe