Scheduling offset for PP/DS stock transport requisitions

187 Views

Hi all

We run CTP (MTS scenario) in our distribution centers where stock transport requisitions are created via PP/DS in order to cover sales orders. We would like to set a an earliest possible start date for the stock transport requisitions of eg. 5 days.

Using planning time fence is not an attractive option as the stock transport requisitions then will be fixed when they get inside the PTF. I have noticed that in the heuristic there is the possibility to set a scheduling offset in minutes, however this does not seem to work for the stock transport requisitions. The start is still current time.

- Does the scheduling offset only work for planned orders (production)?

- Is there any other option than PTF to determine the earliest start date of a PP/DS planning period?

Thank you in advance.