Dec 02, 2009 at 09:50 AM

Network costing

58 Views

When doing network costing the activities are not costed, and the message is that I should maintain the activity type.

But the point is that I have different people assigned to the activity, and they have different activity types in InfoType 315.

So the same activity should be costed based on splits and respective multiple activity types.

How is this possible still to do the costing?