Project settle to FXA error Acquisition value negative in area 96

125 Views

Dear all

could you help me on the following issue.

today, i settle a project to AUC first. it is done correctly.

then i TECO the project and maitain the settle rule for the settlement to FXA.

i do CJ88 and the error occurs Acquisition value negative in area 96

Message no. AA617

does someone know what happened? can someone give me some suggestions or hints?

thanks a lot.