Hi experts
We have been working with a product that can be procured either by External Procurement or In-House Production. When we run the SNP omtimization, it creates production planned orders, but then when we tried to send this orders to ECC it changes his status from SNP planned order to purchase requisition intead of planned orders in ECC.
The question is: ¿why if SNP optmization run plan orders to be In house production why when i send this order to ECC it is changing the status to purchase requisition?
Thanks
David