Former Member
0 Kudos

Hi,

Is there any setting in SAP at plant level or at user profile/parameter level where we can decide if a user can receive in schedule lines/purchase orders due for the future or not?

For eg, a PO is due not until 12/31/2009 but I want to receive it in today. Can that receipt be prevented via some system setting ?

Thanks

GS

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

You can activate the message in customizing for the same ( t.code OMCQ)

Message version : 00

Applicaytion Area : M7

Message id : 254

Category : E

This will give error message while posting the GR and you can stop the goods receipt.

Cheers,

Satish Purandare

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

You can activate the message in customizing for the same ( t.code OMCQ)

Message version : 00

Applicaytion Area : M7

Message id : 254

Category : E

This will give error message while posting the GR and you can stop the goods receipt.

Cheers,

Satish Purandare