Hello,

I would like to know if there is a transaction for massive process of changing cost center .

The issue is to make larger the validity of the cost centers.

Thanks in advance

Olga

Accepted Solutions (0)

Answers (1)

Answers (1)

iklovski
Active Contributor
0 Kudos

Hi Olga,

You have to create these cost centres (KS01) in the new validity date. You can do it via LSMW or CATT functionalities.

Regards,

Eli

Former Member
0 Kudos

Hi Eli!.

I have discovered a transaction-KS07-Rough Entry, where I could do this.

But this is not totally complete, I would need LSMW to load cost center category and responsable person.