Gurus,
Can u pl explain the Preventive Maintenace cycle?
Where it starts & where it ends & the transaction codes
Hello,
Create Single Cycle / Strategy Plan
Schedule the plan
Based on the start date and frequency, system will generate the maintenance orders
Orders can be viewed in IW38 transaction. You can restrict the orders by entering order type that you have chosen for preventive maintenance order (Generally PM02).
After you process the order, confirm the activity duration with t-code IW41.
After that, go to transaction IW32 and complete the order.
Furhter, do business completion after all jobs pertaining to the orders completed.
Hope this will help u.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Gurus,
T code please
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
[SAP Help|http://help.sap.com/erp2005_ehp_04_sp/helpdata/en/3c/abaeaa413911d1893d0000e8323c4f/frameset.htm]
Regards
Narasimhan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.