Conversion of Planned order to PR and Dependent Requirements

193 Views

Hello Everyone,

I had two issues to be dealt with..

1. When i run my MRP run for a specific plant i do not want the system to automatically convert planned orders to Purchase requisitions for specific material in specific plant. How do i Configure the same?

2. I use planning strategy 40 for the header material. During MRP run dependent requirements are automatically raised for lower level components. But how does the user know which planned order is generated for which higher level order?

Moreover, since the same raw material is used in multiple finished materials, a single planned order is raised for the same raw material. This makes it all the more complex.

I think Individual/ Collective requirement does not help in this case because i am using stategy group 40 which is a MTS strategy.

Any help in both these cases would be greatly appreciated..

Sincerely,

Aji

Edited by: Aji Kurian Mani on Nov 28, 2009 2:51 PM