Nov 28, 2009 at 11:14 AM

Explosion date in Master data section of planned order.

379 Views

Hi All

I have MTO scenario

Sales order line item has delivery date 11.12.09

I have setting which causes basic dates to be overwritten by production dates.

I have not maintained any inhouse production time.

When i do MRP with lead time scheduling then i get following dates in planned order.

Order finish -11/12/09

Order start -- 30/11/09

In master data section there is bom explosion date - 26/ 11/2009

Please tell me from where this date is coming ?

I have settings which explodes bom which are vallid of start date of planned order