Explosion date in Master data section of planned order.

former_member240058
Participant
0 Kudos

Hi All

I have MTO scenario

Sales order line item has delivery date 11.12.09

I have setting which causes basic dates to be overwritten by production dates.

I have not maintained any inhouse production time.

When i do MRP with lead time scheduling then i get following dates in planned order.

Order finish -11/12/09

Order start -- 30/11/09

In master data section there is bom explosion date - 26/ 11/2009

Please tell me from where this date is coming ?

I have settings which explodes bom which are vallid of start date of planned order

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Check the scheduling margin key for the material....

former_member240058
Participant
0 Kudos

Hi Dario

There is scheduling margin key 000 is used for the material.

Former Member
0 Kudos

Check if there are any holidays in between....

Former Member
0 Kudos

Check the Note 412736 which explains the logic behind explosion date calculation...

One of the possibilities is that during basic dates scheduling , BoM explosion date is the same as start, but once lead time scheduling is carried out, the initial order date is modified but the explosion date remains unchanged and you noticed the large gap between both dates

former_member240058
Participant
0 Kudos

Hi Dario

In which conditions or business scenario we need explosion date as start date of planned order OR End date of planned order

former_member196398
Active Contributor
0 Kudos

Mayuresh,

I have so far not come across a scenario where the BOM explosion requirement was based on the Finish date of the Planned Order. Generally used is BOM explosion based on Planned order start date or BOM Explosion number.

Business scenario which I can think of for BOM explosion based on finish date is that, when the order procesing time is huge due to number of operations or due to Individual duration required for completion of the operations.

Regards,

Prasobh

Former Member
0 Kudos

Hello,

it is hard to detect the nature of the "inconsistency" you mention without accessing your system, but check the conditions youhave using the Note explanation.

Check that there can be differences in new, modified or new explosion in MRP. So it would be advisable to delete all existing planned orders, run the MRP creating new ones and check out which are the dates in these orders (with basic dates or lead time scheduling)

Additionally you can select the criteria for BoM explosion using OMIW in customizing

Regards