on 11-28-2009 9:38 AM
Dear Guru,
I've created a subcontracting PO for 5000qty,out of which i've issued 3000 to S.C and have also done GR of the same qty.
I've to issue remaining qty to S.C but system give error that PO qty is 0,plz guide me how do i issue the matl S.C.
THANKS & REGARDS
Vjay.
Hi Vijay,
1) Check the GR quantity ( remaining open quantity )
2) Check the BOM relation ship between the ROH material and HALB material in CS02.
3) Also ensure that the item is not deleted in the PO for further processing.
Thanks and Regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Have you checked the plant has sufficient stocks are not?
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi vijay,
Check in mmbe with the material number and plant and check the qty in the line "Matl prov. to vendor", if it shows 2000 then u have issued the full PO qty. So u put GRN for the remaining qty using the PO.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
110 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.