on 11-27-2009 6:50 AM
Hello All,
We are using a Configurable material and i have a question about the configurable material. The Configurable FERT material should be a MTO and all the configured components should be MTS. I want to enter the forecast for the components in Md61 and put them in stock and the requirement from the Configurable finished good should consume the PIRs. can anyone tell me what strategies i should use at each level. Thanks in Advance.
hi
Use strategy 25 at config material and 70 at component level
Regards
Amit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
HI ,
Have u tried solution by Amit,
you try with combination of FERT =25 and HALB=70
and
FERT =25 and HALB = 40 (try both ind. Req indicaotr in MRP 4)
Regards
Raghu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
HI,
USE STRATEGY 56 AT Fert level. this would allow you to plan the requirements at header level in advance and will be transfered to subassemblies during mrp. and pir at header will be consumed by actual sales order.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello
I have tried above suggestion, but they did not work. The sub assemblies (variant components) are not being consumed by the Fert level requirement. It is creating Another new requirement, it is not consuming the PIRS for the sub assemblies. Can someone suggest me what to do here.
Edited by: jags on Nov 28, 2009 5:58 AM