cancel
Showing results for 
Search instead for 
Did you mean: 

hourwise planning and scheduling in planninga table in rem process

Former Member
0 Kudos

Hi

I am in REM process. the scenairo is i have a product group . under this 5 products are produced under the same production line.

we are using Planning table , day wise. Now we going to do the capactiy planning.

how to do in the REM process. any config is needed?

My CLIENT EXPECT THE DATA LIKE. HOUR WISE PRODUCTION FOR THE PRODUCTS.

LIKE 9.00 - 11.00 P1 100 QTY

11.00 - 02.00 P2 100 QTY

02.00 - 05.00 P3 100 QTY

IN THE SAME PORDUCTION LINE. HOUR WISE PRODUCTION .HOW CAN I GET THIS DATA FROM THE PLANNING TABLE. OR

HOW CAN I DO THE PLANNING AND SCHEDULE IN THE PRODUCTION LINE.

Thnaks @Regards

vbraj

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Raj,

In planiang table MF50 you can plan with a samllest period of 1 Day.

for periods oher than this you need to define a planing calendor and on mf50 intial screen in tab-periods and calendor.> select Period as K -plani g calendor and specify the planing calendor. you can plan this as per periods in planing calendor in MF50.

Answers (0)